Welcome

Welcome to Aston-Mansfield’s consultation website for the plans to redevelop the Durning Hall site. Here you can find out more about the plans for the site and the consultation process.

In November, we held our second consultation exercise on the detailed plans for the redevelopment. Like our first stage of consultation, the second stage of consultation also took place ‘at a distance’. We used a range of methods to make sure the consultation was promoted as widely as possible.

We would like to thank everyone who has taken part in the consultation and provided their feedback on the plans. It was great to hear from so many members of the local community on the plans for the redevelopment of the Durning Hall Site.

We are pleased to say that the planning application for the site has now been submitted to Newham Council. The details of the planning application and supporting documents are available to be viewed on Newham Council’s planning portal under the application reference 20/02849/FUL. These are also available to view by clicking here.

On the ‘Have Your Say’ section of this website, you can still view our virtual exhibition boards on the detailed plans and the virtual exhibition boards on the early proposals for the redevelopment.

Site Entrance From Earlham Grove

Update on the redevelopment of the Durning Hall site

As you may be aware, the London Borough of Newham have now approved the planning application for the redevelopment of the Durning Hall site in Forest Gate and Aston-Mansfield has started thinking about the next steps.

We have decided to redevelop the site in partnership with an organisation with development expertise, and are hoping to secure a partner, and partnership agreement by September 2022. We are committed to working with an organisation/partner whose values are aligned with our own and who will meet our expectations in maximising the value of the site.

It is our intention to keep the Durning Hall Community Centre open and running until 2023 and we anticipate that the construction works will commence in or after September 2023. The building works are expected to last at least 2 years with an earliest completion date of August 2025. However, due to the nature of the development, these dates might change slightly.

We will endeavour to keep the local community informed about the works taking place on site by sending regular updates regarding the redevelopment of the site. We would also like to take this opportunity to thank you for your on-going support and use of our services and hope that you are all well and safe.

Sign up to our mailing list!

Sign up to get up-to-date news about the project.



We use reCAPTCHA to help protect this website and its users from spam and abuse. Any information you provide us with, should you wish to do so, will be held securely and processed in line with our privacy policy. You will only be contacted in relation to the project.

get in touch!

If you have any questions about the project, please get in touch

Contact us